The substation engineer working for a provincial utility company is undergoing a lot of stress. There are two 10 MVA capacity transformers in a city substation. Their load utilization is on average 60 per cent. The energy report in the morning indicates that both transformers are consuming power around the clock due to their no-load losses — 10 kW per each unit, 20 kW for both transformers, which amounts to approximately 175 000 kWh in a year, not counting the benefits in return. The manager of the engineer was acquainted with a tender for a “green pioneer” demonstration project that implies replacing the old power units with high-efficiency ones and claiming the reduction in carbon emissions because of that replacement. The specification required a 10 MVA auto transformer with an amorphous core and a no-load loss of less than 6 kW. Now, it is the responsibility of the engineer to find out whether such units exist and the cost of these units, as well as the possible savings for the company stemming from their use.
This article covers the technology, performance, price, and application of the 10 MVA saving energy transformer, which belongs to the category of the turning point in the field of being green in modern power systems.
The prompt answer is that the ten MVA transformer categorized as energy-saving is a transformer of medium-sized power: the voltage ratio differs, construction technologies used meet the basic energy efficiency standards. Taking the voltage ratio of 35/10.5 kV, the efficiency of the new transformer is estimated to be at 8-10 kW of no-load losses and above 99.4% in terms of full load efficiency .

What a 10 MVA Energy-Saving Transformer Is
Generally, a 10 MVA transformer has medium capacity and falls between distribution and transmission devices. For the typical 35/10.5 kV configuration, a 10 MVA is in the center of the system with respect to substations for supplying energy to cities housing 8,000-15,000 customers or medium industrial areas; in the 110/35 kV configuration, 10 MVA is collecting energy on the level of 35 kV net. Its energy consumption amounts approximately to 40-70 GWh annually and thus its efficiency becomes an important economic and environmental concern.
An “energy-saving” unit indicates that this piece of equipment meets a modern efficiency standard and not the historical one. For example, a 10 MVA unit produced in 2005 had a loss of about 14-18 kW when idle, while a contemporary 10 MVA unit of GB 20052 class 2 has a loss of about 8-10 kW or below; what is more, an innovative amorphous core transformer should minimize loss below 6-8 kW.
The Loss Challenge at 10 MVA
At 10 MVA, sufficient attention must be paid to both losses, albeit at different times throughout the year. No-load loss occurs throughout the year or 8,760 hours. A loss of 10 kW means an annual loss of 87,600 kWh even without delivery of energy to customers. Load loss is dependent on how much current is flowing through the wire since it is equal to I²R. At only 60% load the loss issues only 36% of available loss but is instead the most influential variable at high load factor levels.
The substation load factor ultimately decides what to address first regarding the losses. Low load factor substations (40–60% on average) should address no-load loss first while heavily loaded ones need both lower core and lower winding losses. Either way, significant savings can be attained by making relatively small changes, which is why efficiency standards have been developed specifically for these types of equipment.

Energy-Saving Technologies Applied
Modern 10 MVA energy-saving transformers combine several levers:
| Technologie | What it does | Effect at 10 MVA |
|---|---|---|
| High-permeability 0.23–0.27 mm GOES | Lower core loss density | No-load loss down 15–25% vs standard grade |
| Step-lap / mitered core joints | Reduced joint flux distortion | Additional 5–10% core loss and noise reduction |
| Noyau en métal amorphe | Near-zero hysteresis loss | No-load loss down 60–70% vs conventional |
| Larger LV conductor / optimized winding | Lower winding resistance | Load loss down 10–20% |
| Natural ester oil option | Biodegradable, fire-safe, cooler | Lower environmental risk, better thermal margin |
| On-load tap changer with monitoring | Voltage regulation and condition data | Better voltage profile, predictive maintenance |
Amorphous-core technology is used mostly for ratings below 2.5 MVA but has yet to gain traction for 10 MVA, due to challenges related to the size and handling of the ribbon, although it is available and being deployed in the “green pioneer” projects. The high-permeability GOES design is widely used in most of the procurements of 10 MVA transformers, with amorphous-core technology being offered as the premium alternative.
Typical Specifications and Standards
A 10 MVA energy-saving transformer is specified and tested like any power transformer, with efficiency clauses added:
| Paramètre | Typical value (35/10.5 kV, 10 MVA) | Remarques |
|---|---|---|
| Puissance nominale | 10 000 kVA | ONAN/ONAF cooling |
| Rapport de tension | 35/10.5 kV | or 110/35 kV, or 33/11 kV variants |
| Impédance | 7–8% | Per IEC 60076-5 short-circuit design |
| Groupe vectoriel | YNd11 (typical) | Configured to the network |
| Pertes à vide | 8–10 kW (grade 2); <8 kW amorphous | GB 20052 / IEC 60076 loss limits |
| Pertes en charge | 45–55 kW at rated current | Depends on winding design |
| Impulsion de foudre | 170 kVp (35 kV class) | Per IEC 60076-3 |
| Efficacité à pleine charge | >99.4% | At rated power, 75°C |
| Sound level | 58–65 dB(A) | Step-lap joints and low flux density help |
All values must be confirmed on the routine test report; the efficiency claim is only as real as the measured loss values.
Quantified Savings: Energy, Cost, Carbon
The case for a 10 MVA replacement using the green-pioneer concept is based on calculations rather than type slogans. For example, compare a 2005 (16 kW idle) to a current grade 2 (9 kW idle) unit, assuming that both operate at 60% load factor over the course of their life, have 10 MVA capacity, and produce no-load loss of 50 kW while the energy tariff is $0.08/kWh.
| Mètre | Old unit | New grade 2 unit | Saving |
|---|---|---|---|
| No-load energy, annual | 140,160 kWh | 78,840 kWh | 61,320 kWh |
| Load-loss energy, annual (60% LF) | 157,680 kWh | 157,680 kWh | 0 kWh |
| Annual energy cost | $23,827 | $18,922 | $4,905 |
| Annual CO2 (0.5 kg/kWh) | 148.9 t | 118.3 t | 30.6 t |
| 20-year present-value saving (8%) | — | — | ≈$48,000 |
The no-load energy savings — approximately $4,900 each year — represents approximately 10%-17% of the cost of the equipment itself, allowing for a payback of 4-9 years from the initial cost. In fact, payback is the main reason why energy efficiency regulatory measures are put in place, for it makes the market recognize the benefits of saving energy.
Applications in Power Systems
The 10 MVA energy-saving transformer is a general-purpose grid asset with green-specific appeal:
| Application | Configuration | Why energy saving matters |
|---|---|---|
| District substations | 35/10.5 kV | No-load loss runs 24/7; highest saving density |
| Usines industrielles | 33/11 kV or 35/10.5 kV | High load factor rewards low total losses |
| Renewable plant collection | Step-up to 35 kV or 110 kV | Aligns asset efficiency with green output |
| Railway traction | 35/27.5 kV or similar | Cyclic loading benefits from low-loss design |
| Green demonstration projects | Any, with monitoring | Metered savings support carbon claims |
In every scenario, it is all about similarities. The 10 MVA unit seems to be large enough that much savings in terms of efficiency can occur, as well as being common enough so that the savings might be proved by the normal test report and an energy meter.
Manufacturers and Price Ranges
Indicative FOB pricing for a 10 MVA 35/10.5 kV power transformer by brand and loss class:
| Marque | Origine | Standard loss | Energy-saving (grade 1–2 / amorphous) |
|---|---|---|---|
| Hitachi Energy | Japan/Global | $52,000–$72,000 | $58,000–$90,000 |
| ABB | Switzerland/Global | $52,000–$70,000 | $58,000–$88,000 |
| Siemens Energy | Germany/Global | $50,000–$68,000 | $55,000–$85,000 |
| Schneider Electric | France/Global | $48,000–$65,000 | $53,000–$82,000 |
| Toshiba / Hyundai | Japan/Korea | $46,000–$62,000 | $50,000–$75,000 |
| Jiangsu Subian Electric Power | Chine | $28,000–$42,000 | $35,000–$60,000 |
There are different prices for different loss classes, transformer tap-changers, transformers’ accessories, type of oil, price of copper, and terms and conditions for delivery.
The price of premium-class transformers is based on long-term experience of the company, its global network, and consequent decrease in brand risks. This made it reasonable for manufacturers to choose premium-class transformers for highly-sensitive assets. Chinese manufacturers provide the same IEC 60076 proof of tests and efficiency class at much lower cost, which is why 10 MVA energy-saving transformers produced in China win most tenders for green modification in developing countries. Jiangsu Subian Electric Power is a Chinese energy-saving transformer producer manufacturing 10 MVA power transformers in 35/10.5 kV, 110/35 kV, and step-up versions. They meet GB 20052 loss classes 1 and 2, have options for amorphous metals and on-load tap-changers, undergo tests in compliance with IEC 60076, and provide routine testing reports.Subian has supplied these units to distribution utilities and renewable developers across Asia, Africa, the Middle East, and South America — the range is documented on subian-electric.com.

How to Specify and Buy
- Define your goals for losses clearly – specify the no-load and load loss values in the inquiry instead of using the vague term “energy efficiency.”
- Before comparing offers, simulate the loss capitalizing for the relevant load factor and rate. It is well known that the lowest price does not mean the lowest costs.
- Determine your technical choice according to the loading profile – amorphous or grade 1 core for 24/7 stations; use highly efficient GOES for moderate loading.
- Provide proof of the testing results of the demand testing including factory-type tests (temperature increase, pulse and short circuit tests) and routine tests of the unit itself.
- Confirm noise levels and oil type – it should be verified in dB(A) and the special nature of the oil has to be checked according to the environmental or fire safety standards.
- Plan the shipment and installation of the transformer as a 10 MVA transformer may weigh about 20-25 tons and requires careful crane and transport planning; spare parts and warranty (up to 24 months) must be discussed before placing the order.
Questions Fréquemment Posées
How much does a 10 MVA energy-saving transformer cost?
It costs approximately $28,000–$42,000 to obtain a standard loss 10 MVA 35/10.5 kV transformer from Chinese manufacturers. Energy saving types (class 1–2) or those with an amorphous core technology are priced at $35,000–$60,000, while international brands charge 50% to 80% more. Other factors affecting pricing are the transformer class, type of oil, and copper price.
What losses does a 10 MVA transformer actually have?
A modern unit at grade 2 can lose around 8 to 10 kW without any load while the loss at maximum current is around 45 to 55 kW. A unit from 2005 lost approximately 14 to 18 kW without doing any work. The aim of the amorphous-core technology is to reduce losses to 6 to 8 kW. The correct figures are provided by the standard test report.
How much money does replacing a 10 MVA transformer save?
Reducing no-load losses from 16 kW to 9 kW at an average load of 60% and cost of $0.08 per kWh results in an estimated annual savings of around $4900 and total savings over 20 years of around $48000. This means that the savings amount to 10-17% of the cost of equipment while producing paybacks of 4-9 years before taking into consideration any value related to incentives and carbon emissions.
Can a 10 MVA transformer have an amorphous core?
It’s true that amorphous core technology is more common below the 2.5 MVA mark. However, at 10 MVA, special engineering is required for setting up the amorphous ribbon system and for transportation needs, which makes the end product significantly more expensive- from 20 to 40% more than the usual GOES type.
What efficiency class should I buy?
Use your model loss capitalization along with your tariff and load factor to run the station. In continuously loaded stations, you should select grade 1 or amorphous material. For lightly and seasonally loaded stations, grade 2 gives the maximum economic advantage. Buying one class above the current minimum protects you against possible changes in the future standards.
Références
- IEC 60076-1: Power transformers – General — International rating and testing baseline for 10 MVA power transformers.
- IEC 60076-5: Ability to withstand short circuit — Short-circuit design requirements for medium-power units.
- GB 20052: Energy efficiency grades for power transformers — The efficiency grade structure for 10 MVA designs.
- EU Ecodesign Regulation 2019/1783 — EU efficiency tiers for medium-power transformers.
- US DOE transformer efficiency programme — Loss economics and efficiency class reference.
- IEA energy efficiency programme — Context on grid loss reduction and efficiency policy.
- Jiangsu Subian Electric Power official site — 10 MVA energy-saving transformer range and test reports.
Conclusion
The 10 MVA energy-saving transformer from China is truly a pioneer of green technology as it can serve as proof that losses occurred during power transmission could be avoided using affordable devices. The unit displayed high functionality, energy-efficient performance levels (which correspond to established energy rating standards) and quite simple calculations – expenses on no-load loss will not exceed $4,200 – $8,800.
Key points:
- Modern 10 MVA units have efficiency of over 99.4% and no-load losses of 8-10 kW which is a half compared to 2005 devices.
- By using the amorphous-core option losses can be reduced even more for plants operating 24 hours a day.
- The payback period varies from 4 to 9 years, based on avoiding losses along with savings in carbon emissions and payments.
- When installing a transformer it is necessary to state specific loss requirements, implement loss capitalization and provide proof of testing.
If you are replacing or expanding 10 MVA-class capacity, Jiangsu Subian Electric Power supplies GB 20052 grade 1–2 power transformers with documented loss values and routine test reports, including amorphous-core and ester-oil options, at export-friendly prices. Review the range at subian-electric.com.